1) Install the sliding conductor bracket. Use welding or expansion bolts to install the angle steel brackets on the track beams. The erection of the bracket must ensure the flatness of the bracket along the entire line. The plane of the angle steel with the rectangular hole must be in a horizontal plane, and the square hole must be in a line. Generally, steel wires can be used for leveling and alignment. The distance between the two supports of the light sliding contact line is <1.5m.
2) Install the lifting rack on the angle steel bracket. Do not tighten the nut at this time until the sliding contact line is installed and adjusted before tightening.
3) Install the sliding contact wire connector sheath. Insert the sliding wire into the bayonet of the lifting rack and lock it. After installing the sliding wire, level it and tighten the nut of the hanging rack. Install the connector into the other end of the first set of wires, and install the second set of sliding contact wires in the same way. Note that the joint should be smooth and the gap should be <0.5mm.
4) Install the power input section. Install according to the designed power supply method, tighten it, and install the protective cover.
5) Install sheath fixing clips, two on one line.
6) Install the end sheath. Install end sleeves at both ends of the trolley line. The entire trolley line should be carefully inspected after installation. The spacing should be consistent, and the trolley line should be parallel to the crane rail, with a deviation of ≤5mm.
7) Install the current collector and its bracket. The distance between the center line of the collector bracket and the low plane of the lower sheath of the sliding conductor must be H=155mm, and the tip of the ︿-shaped groove of the sliding conductor must be in the same vertical plane as the vertical center line of the collector.
8) Connect the power supply. Connect the power cord firmly to the power input section, tighten it, and test drive.